Progress of LRT Jakarta Phase 1B Construction Reaches 47.13 Percent

The development of Jakarta's LRT Phase 1B, which connects Velodrome - Manggarai over a distance of 6.4 kilometers, continues to show positive progress.

We completed the foundation drilling in Manggarai

PT Jakarta Propertindo (Jakpro) reported that the overall progress of the construction has reached 47.13 percent as of January 31, 2025, covering the structural work of the elevated track with a focus on foundations, bridge pier construction, and bridge beam installation.

LRT Jakarta Phase 1B Project Director, Ramdani Akbar said the project is now progressing following the established targets, with the main focus on the construction of the bridge span structure, starting from the foundation work to the installation of the bridge beams.

Acting Governor Teguh Appreciates LRT Jakarta for Providing Best Service

"Recently, we completed the foundation drilling in Manggarai and the installation of the steel box girder in Rawamangun," he expressed, Friday (2/14).

Besides improving inter-regional connectivity, the LRT Jakarta Phase 1B also supports a more efficient and sustainable transportation system.

He hoped that this infrastructure would become a modern, inclusive, and integrated mass transportation solution, in line with Jakarta's vision as a competitive and sustainable global city.

"Hopefully, this will become an affordable and environmentally friendly urban mobility solution, while also strengthening Jakarta's competitiveness on the global stage," he hoped.

Here are the details of the construction progress of LRT Jakarta Phase 1B:

1. Zone 1 (Velodrome – Rawamangun – Pasar Pramuka)

• Rawamangun Station: Entering the architectural finishing stage, MEP (Mechanical, Electrical, and Plumbing), as well as construction of eastern side entrance.

• BPKP Pramuka Station & Pasar Pramuka Station: Currently in the foundation, pilecap, bridge pylon, and pierhead shoring stages

• Jalan Pemuda, Rawamangun: Installation of steel box girder P34B-P35B has been completed and is now entering the slabdeck work stage

2. Zone 2 (Matraman – Manggarai)

• Matraman Station: Foundation work has been completed, the next stage is the installation of piers and pierheads

• Jalan Tambak: 10 bridge span girders have been installed, currently work is underway on the slabdeck and parapet walls

• Manggarai Station: Foundation drilling is still ongoing, while bridge beam installation is being carried out at points P110B – P113B

As information, the construction of LRT Jakarta Phase 1B is part of Jakarta's major transformation towards a more environmentally friendly and highly competitive global city

This project is slated to be completed in the fourth quarter of 2026, with the hope of encouraging more people to switch to more efficient and sustainable public transportation.

With the extension of the route and integration with the Commuter Line, Mikrotrans, and Transjakarta, LRT Jakarta is expected to serve 80,000 to 100,000 passengers per day.

"Besides speeding up mobility, this project also has the potential to boost the economy around the station area, create new business opportunities, and improve the quality of life for Jakartans," he stated.

Linked News
Popular News indeks
  1. Deputy Gov Rano: Meat Stocks Secured Up to Ramadhan

    access_time22-02-2025 remove_red_eye508 personBudhi Firmansyah Surapati
  2. Jakarta to Hold Cheap Food Bazaar at 193 Locations

    access_time22-02-2025 remove_red_eye411 personBudhi Firmansyah Surapati
  3. Pramono - Rano Expected to Realize Better Resident Welfare

    access_time20-02-2025 remove_red_eye304 personBudhi Firmansyah Surapati
  4. Jakarta Commits to Realizing National Waste Management Pilot Project

    access_time17-02-2025 remove_red_eye289 personFolmer
  5. Batu Ampar and Induk River Connecting Channels Dredged

    access_time16-02-2025 remove_red_eye288 personNurito